Project tracker

All 389 Ministry of Construction projects, with planned and actual progress, as of 1 Jun 2026.

How status is worked out
completed100
on track98
behind plan49
past contract end112
Rehabilitation of the Sabian Mandaean mandi (temple) in Kirkuk Kirkuk Buildings No. 1 No contract end date given On track Rehabilitation of Jalawla General Hospital Diyala Buildings No. 2 Contract ended 18 Apr 2026, 44 days before the data date Past contract end Construction of the National Human Rights Network office building in Anbar Anbar Buildings No. 3 Contract ended 25 Dec 2025, 158 days before the data date Past contract end Construction laboratory building in Anbar Anbar Buildings No. 4 Contract ended 26 Dec 2025, 157 days before the data date Past contract end Supply of imported laboratory equipment for testing construction materials for the National Center for Construction Laboratories in Baghdad and the provinces Baghdad Buildings No. 5 No contract end date given On track Rehabilitation of the minaret of the Khulafa Mosque Baghdad Buildings No. 6 Contract ends 15 Jul 2027 On track Additional floor for the Engineering Reconstruction Directorate building Baghdad Buildings No. 7 Contract ended 1 May 2026, 31 days before the data date Past contract end Reconstruction of the Ministry of Planning building complex (C, D, E, F, H, I, J, K, L) Baghdad Buildings No. 8 10.7 points below planned progress Behind plan Iraqi building codes and application of Arab codes Baghdad Buildings No. 9 No contract end date given On track Rehabilitation of the diplomatic quarter in Baghdad, Amiriya area Baghdad Buildings No. 10 Contract ends 27 Apr 2027 On track Completion works for the Grand Festivities Square and Unknown Soldier Monument, Baghdad Baghdad Buildings No. 11 Contract ends 7 Dec 2026 On track Unified bill of quantities (standard price analysis guide) Baghdad Buildings No. 12 No contract end date given On track Studies, designs and design review for an annex building for the Building Research Directorate Baghdad Buildings No. 13 No contract end date given On track Expansion of the National Center for Engineering Consultancy building Baghdad Buildings No. 14 No contract end date given On track Rehabilitation of the Sabian Mandaean cemetery in Baghdad, Abu Ghraib Baghdad Buildings No. 15 No contract end date given On track Studies, designs and design review for the Karbala traffic directorate building Karbala Buildings No. 16 No contract end date given On track Phase three of the shrine of Martyr Mohammed Baqir al-Sadr Najaf Buildings No. 17 10.3 points below planned progress Behind plan Power supply for the Zurbatiyah border crossing project Wasit Buildings No. 18 No contract end date given On track Zurbatiyah border crossing, remaining works on the passenger building Wasit Buildings No. 19 Contract ended 10 Apr 2026, 52 days before the data date Past contract end Engineering consultancy contract to review the designs of the commercial section Wasit Buildings No. 20 No contract end date given On track Zurbatiyah border crossing, commercial section Wasit Buildings No. 21 Contract ended 17 May 2026, 15 days before the data date Past contract end Rehabilitation of Sabian Mandaean cemeteries in Dhi Qar Dhi Qar Buildings No. 22 No contract end date given On track Construction of the residential complex in Basra Basra Buildings No. 23 No contract end date given On track Cancer treatment and bone marrow transplant center, Duhok Duhok Buildings No. 24 Completed Consultation clinic in Shorish subdistrict, Sulaymaniyah Sulaymaniyah Buildings No. 25 Completed Emergency hospital in Ranya, Sulaymaniyah Sulaymaniyah Buildings No. 26 Completed Urban statistics section building, Nineveh Nineveh Buildings No. 27 Completed Ministry of Planning building complex in Nineveh Nineveh Buildings No. 28 Completed Rehabilitation of Mar Mattai Monastery and construction of the theological institute in Bashiqa Nineveh Buildings No. 29 Completed National Human Rights Network office in Nineveh Nineveh Buildings No. 30 Completed Reconstruction and rehabilitation of the Ministry of Construction offices in Nineveh Nineveh Buildings No. 31 Completed Rest house for Ministry of Construction staff in Kirkuk Kirkuk Buildings No. 32 Completed Rest house for Ministry of Construction staff in Salah al-Din Salah al-Din Buildings No. 33 Completed Statistics building for Balad district Salah al-Din Buildings No. 34 Completed National Human Rights Network office in Salah al-Din Salah al-Din Buildings No. 35 Completed Studies, designs, reconstruction and rehabilitation of the shrine of Sayyid Muhammad bin Ali al-Hadi in Salah al-Din Salah al-Din Buildings No. 36 Completed Studies and designs for the visitors' city at the shrine of Sayyid Muhammad bin Ali al-Hadi in Balad, Salah al-Din Salah al-Din Buildings No. 37 Completed State Real Estate Directorate office buildings in Anbar Anbar Buildings No. 38 Completed Rest house for Ministry of Construction staff in Anbar Anbar Buildings No. 39 Completed Fallujah statistics section headquarters Anbar Buildings No. 40 Completed Rehabilitation of the Grand Festivities Square Baghdad Buildings No. 41 Completed Chaldean Patriarchate of Babylon building and fittings Baghdad Buildings No. 42 Completed Building for the Expressways Directorate Baghdad Buildings No. 43 Completed Building for the General Authority for Buildings Baghdad Buildings No. 44 Completed Building for the Baghdad Roads and Bridges Directorate Baghdad Buildings No. 45 Completed National Human Rights Network office in Babil Babil Buildings No. 46 Completed Studies, designs, reconstruction and rehabilitation of the shrine of Sharifa bint al-Hasan in Babil Babil Buildings No. 47 Completed State Real Estate Directorate office buildings in Karbala Karbala Buildings No. 48 Completed Rest house for Ministry of Construction staff in Karbala Karbala Buildings No. 49 Completed Studies, designs, rehabilitation and reconstruction of the shrine of Awn bin Abdullah in Karbala Karbala Buildings No. 50 Completed Studies, designs and design review for a building for the Directorate for Protection of the Two Holy Shrines in Karbala Karbala Buildings No. 51 Completed Ministry of Construction offices in Karbala Karbala Buildings No. 52 Completed Payments for completed works, dollar exchange rate inflation amounts and unpaid deposits from the Ministry of Interior Wasit Buildings No. 53 Completed State Real Estate Directorate office buildings in Wasit Wasit Buildings No. 54 Completed Central Organization for Standardization and Quality Control building in Wasit Wasit Buildings No. 55 Completed State Real Estate Directorate office buildings in Diwaniyah Al-Qadisiyah (Diwaniyah) Buildings No. 56 Completed Rest house for Ministry of Construction staff in Maysan Maysan Buildings No. 57 Completed Rural housing units in the marshes of Basra, Maysan and Dhi Qar (marshes revival program) Maysan Buildings No. 58 Completed State Real Estate Directorate office buildings in Dhi Qar Dhi Qar Buildings No. 59 Completed State Real Estate Directorate office buildings in Muthanna Muthanna Buildings No. 60 Completed Rest house for Ministry of Construction staff in Muthanna Muthanna Buildings No. 61 Completed Muthanna construction laboratory Muthanna Buildings No. 62 Completed Central Organization for Standardization and Quality Control building, Basra branch Basra Buildings No. 63 Completed Consultancy contract Several provinces Buildings No. 64 Completed Settlement of accounts for completed and cancelled projects of the Ministry of Construction Buildings Directorate Several provinces Buildings No. 65 Completed Soil investigations (National Human Rights Network office) Several provinces Buildings No. 66 Completed Residential complex in Nineveh, Tal Afar Nineveh Housing No. 67 Contract ended 3 Apr 2026, 59 days before the data date Past contract end Residential complex in Nineveh, Makhmur Nineveh Housing No. 68 71 points below planned progress Behind plan Residential complex in Nineveh, Arbajiya Nineveh Housing No. 69 17.5 points below planned progress Behind plan Residential complex in Nineveh, Sinjar Nineveh Housing No. 70 No contract end date given On track Residential complex in Salah al-Din, Mutarada Salah al-Din Housing No. 71 28.7 points below planned progress Behind plan Residential complex in Salah al-Din, Armushiya Salah al-Din Housing No. 72 36 points below planned progress Behind plan Residential complex in Diyala, Khalis Diyala Housing No. 73 Contract ended 30 May 2024, 732 days before the data date Past contract end Residential complex in Diyala, Ghalibiya Diyala Housing No. 74 Contract ended 8 Jul 2024, 693 days before the data date Past contract end Residential complex in Diyala, Katoun Diyala Housing No. 75 47.2 points below planned progress Behind plan Residential complex in Anbar, Hit Anbar Housing No. 76 Contract ends 24 Nov 2027 On track Residential complex in Anbar, Jubail and Kharab Anbar Housing No. 77 Contract ends 16 Sept 2027 On track Residential complex in Anbar, Amiriyat al-Fallujah Anbar Housing No. 78 No progress data Residential complex in Baghdad, Nahrawan Baghdad Housing No. 79 No contract end date given On track Residential complex in Babil, Qasim Babil Housing No. 80 89.2 points below planned progress Behind plan Residential complex in Karbala, Jazeera 2 Karbala Housing No. 81 Contract ended 14 May 2024, 748 days before the data date Past contract end Residential complex in Karbala, Jazeera 1 Karbala Housing No. 82 80.7 points below planned progress Behind plan Residential complex in Wasit, Aziziya Wasit Housing No. 83 Contract ended 4 Sept 2025, 270 days before the data date Past contract end Residential complex in Wasit, Suwaira Wasit Housing No. 84 Contract ends 5 Jun 2026 On track Residential complex in Wasit, Zurbatiyah Wasit Housing No. 85 Contract ends 1 Jun 2026 On track Residential complex in Diwaniyah, Housing Department homes Al-Qadisiyah (Diwaniyah) Housing No. 86 Contract ended 3 Nov 2021, 1,671 days before the data date Past contract end Residential complex in Diwaniyah, Afak Al-Qadisiyah (Diwaniyah) Housing No. 87 18 points below planned progress Behind plan Residential complex in Diwaniyah, Jibsa and Shamiya Al-Qadisiyah (Diwaniyah) Housing No. 88 Contract ended 11 Jul 2025, 325 days before the data date Past contract end Residential complex in Diwaniyah, Daghara Al-Qadisiyah (Diwaniyah) Housing No. 89 No contract end date given On track Residential complex in Diwaniyah, Shanafiya Al-Qadisiyah (Diwaniyah) Housing No. 90 11.8 points below planned progress Behind plan Residential complex in Diwaniyah, Hamza al-Sharqi Al-Qadisiyah (Diwaniyah) Housing No. 91 14.2 points below planned progress Behind plan Residential complex in Maysan, Abu Rumana Maysan Housing No. 92 Contract ended 21 Feb 2026, 100 days before the data date Past contract end Residential complex in Maysan, Qal'at Salih Maysan Housing No. 93 No contract end date given On track Residential complex in Maysan, Martyrs Foundation Maysan Housing No. 94 19.1 points below planned progress Behind plan Residential complex in Maysan, Majar al-Kabir Maysan Housing No. 95 No contract end date given On track Residential complex in Maysan, Kumait Maysan Housing No. 96 62.7 points below planned progress Behind plan Residential complex in Dhi Qar, Shatra Dhi Qar Housing No. 97 No contract end date given On track Residential complex in Dhi Qar, Qal'at Sukkar Dhi Qar Housing No. 98 No contract end date given On track Residential complex in Dhi Qar, Suq al-Shuyukh Dhi Qar Housing No. 99 67.6 points below planned progress Behind plan Residential complex in Dhi Qar, Akaika Dhi Qar Housing No. 100 27.8 points below planned progress Behind plan Residential complex in Dhi Qar, Kashmara 1 Dhi Qar Housing No. 101 Contract ended 9 Jan 2024, 874 days before the data date Past contract end Residential complex in Muthanna, Rumaitha Muthanna Housing No. 102 52.1 points below planned progress Behind plan Residential complex in Muthanna, Jarbouiya Muthanna Housing No. 103 67.7 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 1 Basra Housing No. 104 Contract ended 20 Dec 2021, 1,624 days before the data date Past contract end Residential complex in Basra, Zubair Basra Housing No. 105 31.3 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 3 Basra Housing No. 106 16.1 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 2 Basra Housing No. 107 48.2 points below planned progress Behind plan Residential complex in Basra, Qibla Basra Housing No. 108 No contract end date given On track Hamdaniya sewage project, Nineveh, with phase two of the networks, treatment plant and infrastructure works Nineveh Sewage No. 109 Contract ends 25 Aug 2026 On track Design review, supply, construction, operation and maintenance of the Bartella sewage network and plant, Nineveh (design capacity 4,942 m3 per day) Nineveh Sewage No. 110 Contract ended 3 Jan 2026, 149 days before the data date Past contract end Supply and construction of the treatment plant for the left bank of Mosul (phase one) Nineveh Sewage No. 111 Contract ends 8 Jun 2026 On track Supply and construction of stormwater trunk lines with lift stations SL46 and SL47, left bank of Mosul Nineveh Sewage No. 112 Contract ended 9 Jan 2026, 143 days before the data date Past contract end Supply and construction of sewage trunk lines with four lift stations, left bank of Mosul, phase four Nineveh Sewage No. 113 Contract ended 3 Feb 2025, 483 days before the data date Past contract end Supply and construction of the treatment plant for the right bank of Mosul, phase 1 Nineveh Sewage No. 114 Contract ended 14 Jul 2024, 687 days before the data date Past contract end Supply and construction of the treatment plant for the right bank of Mosul, phase 2 Nineveh Sewage No. 115 Contract ends 12 Jan 2027 On track Supply and construction of the treatment plant for the left bank of Mosul (phase two) Nineveh Sewage No. 116 Contract ended 14 Apr 2024, 778 days before the data date Past contract end Supply and construction of stormwater trunk lines with a lift station, right bank of Mosul, phase 4 Nineveh Sewage No. 117 Contract ended 10 Feb 2025, 476 days before the data date Past contract end Sewage networks project, right bank of Mosul Nineveh Sewage No. 118 Contract ends 5 Nov 2026 On track Study and design of a treatment plant with main and branch stormwater and sewage networks and lift stations for central Kirkuk, with supply, construction, operation and maintenance of phase one (turnkey) Kirkuk Sewage No. 119 Contract ends 28 Aug 2027 On track Hawija district sewage project, Kirkuk (infrastructure) Kirkuk Sewage No. 120 Contract ends 17 May 2028 On track Altun Kupri district sewage, Kirkuk (infrastructure) Kirkuk Sewage No. 121 Contract ends 18 Sept 2028 On track Supply, construction, operation and maintenance of the treatment plant, sewage and stormwater networks, lift stations, trunk lines and outfalls for Samarra, phase 2 Salah al-Din Sewage No. 122 Contract ended 27 Dec 2024, 521 days before the data date Past contract end Supply, construction, operation and maintenance of completion works for stormwater and sewage networks with lift stations for unserved neighbourhoods of Dujail Salah al-Din Sewage No. 123 Contract ends 11 Jul 2027 On track Completion works for the Balad treatment plant, phase 2, Salah al-Din, with supply, construction, operation and maintenance of phase 2 of the plant Salah al-Din Sewage No. 124 15.1 points below planned progress Behind plan Completion works for the Tikrit (Dhuba'i) treatment plant, phase 2 Salah al-Din Sewage No. 125 Contract ended 7 Nov 2025, 206 days before the data date Past contract end Completion of study, design and construction of Siniya sewage (turnkey) with infrastructure development for Siniya subdistrict Salah al-Din Sewage No. 126 Contract ends 23 Aug 2028 On track Stormwater and sewage networks and stations for Dayoum, Tikrit district, with infrastructure development for Tikrit and Dour districts Salah al-Din Sewage No. 127 Contract ends 9 Jun 2028 On track Phase two of the Baiji sewage project, Salah al-Din (infrastructure) Salah al-Din Sewage No. 128 No progress data Supply, construction, operation and maintenance of completion works for the stormwater and sewage networks, lift stations and treatment plant of Khalis Diyala Sewage No. 129 12.7 points below planned progress Behind plan Supply, construction, operation and maintenance of completion works for stormwater and sewage networks with lift stations and treatment plant for Baquba, phase 2, Diyala Diyala Sewage No. 130 Contract ended 27 Feb 2026, 94 days before the data date Past contract end Fallujah sewage project, capacity 35,000 m3 per day (turnkey) Anbar Sewage No. 131 Contract ended 18 Apr 2026, 44 days before the data date Past contract end Integrated sanitation with a treatment unit for the city of Hit in Anbar Anbar Sewage No. 132 Contract ends 12 Dec 2026 On track Stormwater and sewage networks for Zones 14 and 15 in Ramadi, part of the Ramadi sewage project, phase 1, Anbar Anbar Sewage No. 133 Contract ended 13 Jul 2024, 688 days before the data date Past contract end Supply and construction of the stormwater drainage trunk line for the southern area, Fallujah Anbar Sewage No. 134 Contract ended 22 Mar 2026, 71 days before the data date Past contract end Sewage and stormwater networks for Ana subdistrict, Anbar (infrastructure) Anbar Sewage No. 135 Contract ends 8 Jun 2028 On track Sewage and stormwater networks for Kubaisa subdistrict, Anbar (infrastructure) Anbar Sewage No. 136 No progress data Stormwater and sewage networks, trunk lines, lift stations and treatment plant for Kifl subdistrict, Babil (infrastructure) Babil Sewage No. 137 No progress data Stormwater networks and trunk lines to the lift station for Qasim, Hashimiya and Madhatiya, Babil (infrastructure) Babil Sewage No. 138 Contract ends 15 Nov 2029 On track Supply and construction of sewage networks for residential neighbourhoods, Karbala, phase 4 Karbala Sewage No. 139 Contract ended 13 Jul 2024, 688 days before the data date Past contract end Najaf sewage treatment plant, phase 3 (design and build), Najaf Najaf Sewage No. 140 No progress data Haidariya city sewage project, Najaf (infrastructure) Najaf Sewage No. 141 No progress data Al-Nidaa neighbourhood sewage project, Najaf (infrastructure) Najaf Sewage No. 142 Contract ends 25 Jun 2028 On track Completion of remaining works on the Aziziya sewage network, Wasit Wasit Sewage No. 143 Contract ended 11 Nov 2025, 202 days before the data date Past contract end Infrastructure rehabilitation and development, phase two, Hay district Wasit Sewage No. 144 Contract ends 27 Feb 2027 On track Al-Bashaer sewage project, Wasit (infrastructure) Wasit Sewage No. 145 Contract ends 26 Apr 2027 On track Diwaniyah sewage project, phase 2, capacity 100,000 m3 per day (turnkey), with Noor Al-Ufuq added as main partner Al-Qadisiyah (Diwaniyah) Sewage No. 146 Contract ended 14 Jan 2026, 138 days before the data date Past contract end Ghammas sewage project, phase 1 Al-Qadisiyah (Diwaniyah) Sewage No. 147 32 points below planned progress Behind plan Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Sunniya district, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 148 Contract ended 31 Mar 2026, 62 days before the data date Past contract end Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Mahnawiya district, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 149 29 points below planned progress Behind plan Afak sewage project Al-Qadisiyah (Diwaniyah) Sewage No. 150 Contract ends 24 Dec 2028 On track Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Sumer district Al-Qadisiyah (Diwaniyah) Sewage No. 151 Contract ends 23 Oct 2026 On track Rehabilitation of 12 residential neighbourhoods in Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 152 Contract ended 21 May 2026, 11 days before the data date Past contract end 21 lift stations in Diwaniyah province Al-Qadisiyah (Diwaniyah) Sewage No. 153 Contract ends 22 Jul 2027 On track Study, design, construction, supply, operation and maintenance of the Ayman al-Shamiya treatment plant, right bank, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 154 Contract ends 26 Jan 2027 On track Study, design, construction, supply, operation and maintenance of the Al Budair treatment plant, capacity 10,000 m3 per day, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 155 10.9 points below planned progress Behind plan Remaining works on neighbourhood networks, phases 2 and 3, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 156 Contract ends 31 Jan 2027 On track Street rehabilitation in the Mechanic, Nahda 1 and Wafaa neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 157 No progress data Street rehabilitation in Hakim 3 neighbourhood Al-Qadisiyah (Diwaniyah) Sewage No. 158 No progress data Street rehabilitation in the Istiqama and Jamiya neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 159 No progress data Street rehabilitation in the Uruba 3, Muallimin and Shuhada neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 160 No progress data Street rehabilitation in the Sob al-Shamiya and Zahraa (behind the center) neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 161 No progress data Street rehabilitation in the Dubbat 1, Dubbat 2 and Adhariya neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 162 No progress data Street rehabilitation in the Turath and Thaqafi neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 163 No progress data Street rehabilitation in the Sinai and Shalabiya neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 164 No progress data Street rehabilitation in the Ziraiyin, Ramadan and Tamim neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 165 No progress data Street rehabilitation in Hakim 1 neighbourhood Al-Qadisiyah (Diwaniyah) Sewage No. 166 No progress data Street rehabilitation in the Abrar, Ansar and Adala neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 167 No progress data Street rehabilitation in the Uruba 1 and Uruba 2 neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 168 No progress data Street rehabilitation in Jazair neighbourhood Al-Qadisiyah (Diwaniyah) Sewage No. 169 No progress data Sewage and stormwater networks and trunk lines to the treatment plant of Shafiya district, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 170 Contract ends 12 Aug 2027 On track Sewage and stormwater networks and trunk lines to the treatment plant of Nuffar district, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 171 Contract ends 18 Sept 2027 On track Street rehabilitation in the Taqiya 1, 2 and 3 neighbourhoods Al-Qadisiyah (Diwaniyah) Sewage No. 172 No progress data Street rehabilitation in the Akrad neighbourhoods (Shahid al-Mihrab and Hakim 2) Al-Qadisiyah (Diwaniyah) Sewage No. 173 No progress data Sewage and stormwater networks and trunk lines to the treatment plant of Salahiya district, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 174 Contract ends 22 Jul 2027 On track Sewage and stormwater networks, trunk lines, lift stations, force mains and the Sudair treatment plant, Diwaniyah Al-Qadisiyah (Diwaniyah) Sewage No. 175 No progress data Design and construction of sewage for Uzair and Ali al-Gharbi districts with an intermediate lift station linking the trunk line to the treatment plant, Maysan (infrastructure, design and build) Maysan Sewage No. 176 No progress data Supply and construction of two Nasiriyah treatment plants (Sob al-Jazira, design capacity 70,000 m3 per day, and Sob al-Shamiya, 65,000 m3 per day) Dhi Qar Sewage No. 177 17.3 points below planned progress Behind plan Study and design of the Shatra sewage project (treatment plant with stormwater and sewage networks and lift stations) with supply, construction and maintenance of phase one (turnkey) Dhi Qar Sewage No. 178 Contract ends 6 Feb 2028 On track Infrastructure for Suq al-Shuyukh district, Dhi Qar Dhi Qar Sewage No. 179 Contract ends 30 Jul 2029 On track Design update and construction of a treatment plant for Warka district, capacity 12,500 m3 per day, Muthanna (infrastructure) Muthanna Sewage No. 180 No progress data Design and construction of an integrated sewage project in Khidr district: treatment plant of 25,000 m3 per day with stormwater and sewage networks and stations, plus roads, lighting and water networks, Muthanna (infrastructure) Muthanna Sewage No. 181 No progress data Design update and construction of a treatment plant for Hilal and Majd districts, capacity 20,000 m3 per day, plus a sewage treatment plant for Ghadir residential city (design and build), Muthanna Muthanna Sewage No. 182 No progress data Design update and construction of a treatment plant for Najmi district, capacity 12,500 m3 per day, Muthanna (infrastructure) Muthanna Sewage No. 183 No progress data Design update and review, supply and construction of stormwater and sewage networks and stations for Samawah (small bank), with a treatment plant of 50,000 m3 per day, Muthanna (infrastructure) Muthanna Sewage No. 184 No progress data Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 4) Basra Sewage No. 185 Contract ends 6 Oct 2026 On track Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 5) Basra Sewage No. 186 Contract ends 21 Dec 2026 On track Supply, construction and installation of the Najaf sewage treatment plant, phase 2, design capacity 100,000 m3 per day Najaf Sewage No. 187 Completed Infrastructure development and rehabilitation for Hay district Wasit Sewage No. 188 Completed Infrastructure development and rehabilitation for Suwaira district Wasit Sewage No. 189 Completed Completion works for the Rifai treatment plant, design capacity 60,000 m3 per day (carried out at the expense of the defaulting company Al-Barih) Dhi Qar Sewage No. 190 Completed Mosul to Sinjar ring road within Tal Afar municipality, 8,050 m, Nineveh Nineveh Municipal services No. 191 24.8 points below planned progress Behind plan Completion works for the Kirkuk building Kirkuk Municipal services No. 192 Contract ended 2 Feb 2026, 119 days before the data date Past contract end Approaches to the Dalla overpass, Salah al-Din Salah al-Din Municipal services No. 193 35.7 points below planned progress Behind plan Rehabilitation of the main road from Jalawla bridge to the Halwan intersection, Jalawla, Diyala Diyala Municipal services No. 194 Contract ended 27 Feb 2026, 94 days before the data date Past contract end Model sanitary landfill in Ramadi Anbar Municipal services No. 195 Contract ended 5 Nov 2025, 208 days before the data date Past contract end Uruba (Radio) overpass, Diwaniyah Al-Qadisiyah (Diwaniyah) Municipal services No. 196 Contract ended 22 Nov 2025, 191 days before the data date Past contract end Jumhuriya intersection overpass, Diwaniyah Al-Qadisiyah (Diwaniyah) Municipal services No. 197 Contract ended 31 May 2024, 731 days before the data date Past contract end Rehabilitation of the Daghara ring road, Diwaniyah Al-Qadisiyah (Diwaniyah) Municipal services No. 198 Contract ended 26 Aug 2025, 279 days before the data date Past contract end Textile (Naseej) overpass, Diwaniyah Al-Qadisiyah (Diwaniyah) Municipal services No. 199 48.9 points below planned progress Behind plan Overpass intersections in Maysan, Butaira Maysan Municipal services No. 200 Contract ended 2 Sept 2025, 272 days before the data date Past contract end Completion works for street paving and development of the Zahraa and Batool residential neighbourhoods, Ali al-Gharbi district Maysan Municipal services No. 201 Contract ended 15 May 2025, 382 days before the data date Past contract end Overpass intersections in Maysan, Karama Maysan Municipal services No. 202 Contract ended 2 Mar 2025, 456 days before the data date Past contract end Overpass intersection in Dhi Qar, Iskan intersection Dhi Qar Municipal services No. 203 Contract ended 23 Jun 2024, 708 days before the data date Past contract end Overpass intersection in Muthanna, Quds intersection Muthanna Municipal services No. 204 Contract ended 13 Oct 2024, 596 days before the data date Past contract end Roads in the industrial area of Halabja Halabja Municipal services No. 205 Completed Concrete paving, second section of Briko quarter, Sayid Sadiq district Halabja Municipal services No. 206 Completed Qayyarah, Shura and Tal Abta water project, Nineveh (2010) Nineveh Water No. 207 Contract ended 18 Mar 2025, 440 days before the data date Past contract end Alqosh water project in Nineveh (2009) Nineveh Water No. 208 Contract ends 24 Apr 2027 On track National water and sanitation master plan for the cities, districts and subdistricts of Kirkuk Kirkuk Water No. 209 23 points below planned progress Behind plan Taza water project in Kirkuk (2011) Kirkuk Water No. 210 Contract ended 28 Jun 2025, 338 days before the data date Past contract end Balad water project in Salah al-Din (2009) Salah al-Din Water No. 211 Contract ends 13 Nov 2027 On track Baiji Siniya water project, capacity 5,000 m3 per hour, and rehabilitation of the unified Baiji water project, 3,000 m3 per hour Salah al-Din Water No. 212 Contract ends 2 Jun 2027 On track Qadisiya water project in Salah al-Din (2009) Salah al-Din Water No. 213 Contract ends 12 Jan 2028 On track Khan Bani Saad water project in Diyala (2004) Diyala Water No. 214 43.6 points below planned progress Behind plan West Baquba water project, capacity 6,000 m3 per hour Diyala Water No. 215 Contract ends 7 Jan 2028 On track Qara Tapa water project, capacity 2,000 m3 per hour Diyala Water No. 216 Contract ends 13 Jul 2028 On track Jalawla water project, capacity 2,000 m3 per hour Diyala Water No. 217 Contract ends 25 Jun 2028 On track Al-Salam and Al-Sarajiq water project in Mansuriya Diyala Water No. 218 Contract ended 11 Apr 2023, 1,147 days before the data date Past contract end Jadidat al-Shatt water project in Diyala (2012) Diyala Water No. 219 Contract ended 24 Mar 2026, 69 days before the data date Past contract end East Husaiba water project in Anbar (2024) Anbar Water No. 220 Contract ends 11 Sept 2027 On track Baghdadi water project in Anbar (2008) Anbar Water No. 221 Contract ended 3 Apr 2024, 789 days before the data date Past contract end Fallujah water project in Anbar (2004) Anbar Water No. 222 Contract ends 2 Aug 2026 On track Kartan water project, capacity 1,000 m3 per hour Anbar Water No. 223 33.5 points below planned progress Behind plan Ramadi water project, capacity 10,000 m3 per hour Anbar Water No. 224 Contract ends 2 Dec 2028 On track Zuhur subdistrict water project in Baghdad (2010) Baghdad Water No. 225 Contract ended 2 Sept 2025, 272 days before the data date Past contract end Nahrawan water project in Baghdad (2008) Baghdad Water No. 226 Contract ended 11 May 2024, 751 days before the data date Past contract end Kifl water project in Babil (2012) Babil Water No. 227 Contract ends 3 Apr 2027 On track Unified Hashimiya and Madhatiya water project Babil Water No. 228 Contract ended 25 Jul 2020, 2,137 days before the data date Past contract end Musayyib, Iskandariya and Jurf al-Sakhar water project in Babil (2009) Babil Water No. 229 Contract ends 19 Jun 2026 On track National water and sanitation master plan for the cities, districts and subdistricts of Karbala Karbala Water No. 230 Contract ended 12 Feb 2026, 109 days before the data date Past contract end Khairat and western Jadwal water project in Karbala (2010) Karbala Water No. 231 Contract ends 15 May 2027 On track South Karbala water project Karbala Water No. 232 Contract ends 3 Sept 2029 On track National water and sanitation master plan for the cities, districts and subdistricts of Najaf Najaf Water No. 233 19.6 points below planned progress Behind plan Unified Najaf and Kufa water project (2008) Najaf Water No. 234 14.8 points below planned progress Behind plan National water and sanitation master plan for the cities, districts and subdistricts of Wasit Wasit Water No. 235 23.3 points below planned progress Behind plan Zubaidiya water project in Wasit (2007) Wasit Water No. 236 Contract ended 15 Dec 2025, 168 days before the data date Past contract end Water trunk lines in Diwaniyah Al-Qadisiyah (Diwaniyah) Water No. 237 Contract ends 26 Jan 2027 On track National water and sanitation master plan for the cities, districts and subdistricts of Diwaniyah Al-Qadisiyah (Diwaniyah) Water No. 238 34.2 points below planned progress Behind plan Daghara and Sumer water project in Diwaniyah Al-Qadisiyah (Diwaniyah) Water No. 239 Contract ends 8 Feb 2027 On track Shafiya water project in Diwaniyah (2024) Al-Qadisiyah (Diwaniyah) Water No. 240 Contract ended 24 Jan 2026, 128 days before the data date Past contract end Shamiya water project in Diwaniyah (2010) Al-Qadisiyah (Diwaniyah) Water No. 241 Contract ended 31 Jul 2025, 305 days before the data date Past contract end Mahnawiya water project, capacity 1,000 m3 per hour Al-Qadisiyah (Diwaniyah) Water No. 242 Contract ends 14 Dec 2026 On track Maimuna water project, capacity 2,000 m3 per hour Maysan Water No. 243 Contract ends 10 Mar 2028 On track Amarah water project in Maysan (2004) Maysan Water No. 244 Contract ended 31 Mar 2025, 427 days before the data date Past contract end National water and sanitation master plan for the cities, districts and subdistricts of Maysan Maysan Water No. 245 Contract ends 26 Oct 2026 On track National water and sanitation master plan for the cities, districts and subdistricts of Dhi Qar Dhi Qar Water No. 246 Contract ended 13 May 2026, 19 days before the data date Past contract end Nasiriyah water project in Dhi Qar (2012) Dhi Qar Water No. 247 No contract end date given On track Samawah water project Muthanna Water No. 248 Contract ended 16 Mar 2025, 442 days before the data date Past contract end National water and sanitation master plan for the cities, districts and subdistricts of Muthanna Muthanna Water No. 249 11.6 points below planned progress Behind plan Greater Basra water project, phase one Basra Water No. 250 Contract ends 27 Feb 2027 On track Greater Basra water project, phase two Basra Water No. 251 No contract end date given On track Study on desalination of drainage and sewage water Several provinces Water No. 252 Contract ends 20 Jul 2026 On track Dujail water project, capacity 4,000 m3 per hour Salah al-Din Water No. 253 Completed Kut water project, capacity 10,000 m3 per hour Wasit Water No. 254 Completed Review of studies for the Samarra, Baladruz and Zanbour projects Several provinces Water No. 255 Completed Second carriageway of the Mosul to Kirkuk road, 124.43 km, in Kirkuk and Nineveh Nineveh Roads and bridges No. 256 Contract ends 24 Apr 2027 On track Ring road with the Seventh Bridge Nineveh Roads and bridges No. 257 Contract ends 21 Dec 2030 On track Rehabilitation of the Sinjar to Umm Jurais road, 35 km long and 7.4 m wide Nineveh Roads and bridges No. 258 Contract ended 22 Jan 2026, 130 days before the data date Past contract end New Kuwair bridge, second carriageway next to the old Kuwair bridge Nineveh Roads and bridges No. 259 Contract ends 21 Jun 2028 On track Rehabilitation and maintenance of the remaining parts of the Daquq bridge Kirkuk Roads and bridges No. 260 Contract ends 20 Jul 2026 On track Maintenance of the Kirkuk to Sulaymaniyah road Kirkuk Roads and bridges No. 261 Contract ended 23 Mar 2026, 70 days before the data date Past contract end Rehabilitation and maintenance of the Baghdad to Kirkuk road, 162 km Kirkuk Roads and bridges No. 262 Contract ended 2 Nov 2024, 576 days before the data date Past contract end Maintenance of the Baiji to Shirqat junction road Salah al-Din Roads and bridges No. 263 Contract ended 22 Nov 2025, 191 days before the data date Past contract end Tikrit concrete bridge (north Tikrit bridge), approaches, phase two Salah al-Din Roads and bridges No. 264 Contract ended 10 Feb 2026, 111 days before the data date Past contract end Balad intersection overpasses on the Baghdad to Mosul road Salah al-Din Roads and bridges No. 265 Contract ends 30 Jun 2026 On track Zghaiton and Al-Shai bridges on the alternative Tikrit to Tuz road Salah al-Din Roads and bridges No. 266 Contract ended 23 Aug 2021, 1,743 days before the data date Past contract end Hamrin lake concrete bridge and rehabilitation of the Muqdadiya to Saadiya main road (Hamrin lake basin) Diyala Roads and bridges No. 267 Contract ended 19 May 2026, 13 days before the data date Past contract end Rehabilitation and maintenance of the Baghdad to Kirkuk road, 110 km Diyala Roads and bridges No. 268 Contract ended 20 Jul 2024, 681 days before the data date Past contract end Maintenance and stabilisation of the Mundhiriya, Imam Wais and Failaq road, 90 km, two lanes Diyala Roads and bridges No. 269 Contract ended 26 Apr 2026, 36 days before the data date Past contract end Sindiya bridge, 336 m Diyala Roads and bridges No. 270 Contract ended 2 Aug 2024, 668 days before the data date Past contract end Various roads across Khalis and its subdistricts in Diyala Diyala Roads and bridges No. 271 Contract ended 13 Sept 2025, 261 days before the data date Past contract end Completion works for a group of roads in Saadiya, Jizani al-Imam and Mansuriya Diyala Roads and bridges No. 272 Contract ends 26 Jul 2026 On track Second carriageway of the Hit to Haditha road, section two, from km 25 to km 50 Anbar Roads and bridges No. 273 Contract ends 15 Jul 2026 On track Widening of the embankment from the Saqlawiya concrete bridge to expressway intersection 51, 14.6 km, with a 2 km service road for low cost housing and a 1.7 km road from the Japanese bridge to the Nazim bridge Anbar Roads and bridges No. 274 Contract ended 10 May 2026, 22 days before the data date Past contract end Rehabilitation of the Ramadi to Rahaliya road, starting at the Kahawi area Anbar Roads and bridges No. 275 Contract ended 25 Aug 2025, 280 days before the data date Past contract end Maintenance and rehabilitation of the road linking Nukhaib and Karbala Anbar Roads and bridges No. 276 Contract ended 24 Apr 2026, 38 days before the data date Past contract end Ring and link roads for Ali al-Wardi city Baghdad Roads and bridges No. 277 32.5 points below planned progress Behind plan Reconstruction of the Rustamiya bridge Baghdad Roads and bridges No. 278 Contract ended 1 Dec 2025, 182 days before the data date Past contract end Grand Baghdad bridge Baghdad Roads and bridges No. 279 Contract ended 1 Apr 2026, 61 days before the data date Past contract end Fadhiliya concrete bridge, Baghdad Baghdad Roads and bridges No. 280 Contract ended 9 Feb 2026, 112 days before the data date Past contract end Design and construction of the Zafaraniya bridge on the Dora to Yusufiya expressway road, reaching Harith bin Kalda street, with an overpass on the Dora to Yusufiya road, Baghdad Baghdad Roads and bridges No. 281 19 points below planned progress Behind plan New bridge over the Tigris with rehabilitation of the old Sarafiya bridge, two overpasses at the Sarafiya bridge and Buratha mosque intersections, and widening of the road between Sarafiya bridge and the Shalchiya intersection (second traffic congestion package) Baghdad Roads and bridges No. 282 Contract ended 28 Nov 2025, 185 days before the data date Past contract end Design and construction of the road linking the Mohammed al-Qasim expressway and the Kirkuk to Baghdad road through Basatin and Suraidat, Baghdad Baghdad Roads and bridges No. 283 Contract ended 22 Dec 2024, 526 days before the data date Past contract end Design and construction of an overpass at the Refinery intersection, linking the Double Decker bridge to the Suspension bridge, and a tunnel at Ahmed Orabi square, Baghdad Baghdad Roads and bridges No. 284 Contract ended 20 Sept 2025, 254 days before the data date Past contract end Design and construction of the Abu Nuwas road widening and the new Jadriya overpass linked to the Nusoor square approaches via Umm al-Khanazir island, Baghdad Baghdad Roads and bridges No. 285 Contract ended 22 Feb 2025, 464 days before the data date Past contract end Design and construction of the Kraiyat bridge, Baghdad Baghdad Roads and bridges No. 286 34.8 points below planned progress Behind plan Dora overpass on 60th street Baghdad Roads and bridges No. 287 Contract ended 10 Oct 2025, 234 days before the data date Past contract end Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel Baghdad Roads and bridges No. 288 82 points below planned progress Behind plan Development of the Ministry of Transport tunnel Baghdad Roads and bridges No. 289 No progress data Shomali to Qasim road linked to the Qasim to Kifl road, 16.48 km Babil Roads and bridges No. 290 Contract ended 25 Mar 2026, 68 days before the data date Past contract end Widening of the Kifl to Najaf road, 10.325 km Babil Roads and bridges No. 291 Contract ended 14 Jan 2026, 138 days before the data date Past contract end Second carriageway linking Haswa city to the expressway Babil Roads and bridges No. 292 Contract ends 3 Aug 2027 On track Maintenance of the Thermostone road, old lane, 10.5 km Karbala Roads and bridges No. 293 Contract ended 26 May 2025, 371 days before the data date Past contract end Rehabilitation of the Baghdad to Karbala road from the Dalla roundabout to checkpoint 54, Karbala Karbala Roads and bridges No. 294 Contract ends 21 Aug 2027 On track Maintenance and resurfacing of the Karbala, Razzaza and Ukhaidir road, phase one Karbala Roads and bridges No. 295 Contract ended 29 Apr 2026, 33 days before the data date Past contract end Partial ring road for Karbala Karbala Roads and bridges No. 296 Contract ends 14 Mar 2029 On track Second carriageway linking the Kifl to Qasim expressway, 30 km, Najaf (infrastructure) Najaf Roads and bridges No. 297 Contract ends 29 Aug 2028 On track Overland Hajj road (239 km), phase two, 50 km from km 77 to km 127, Najaf Najaf Roads and bridges No. 298 11.5 points below planned progress Behind plan Widening of the Haidariya to Najaf and Karbala road, 15.64 km Najaf Roads and bridges No. 299 Contract ends 13 Jul 2026 On track Overland Hajj road (239 km), phase one, 50 km from km 27 to km 77, Najaf Najaf Roads and bridges No. 300 Contract ended 7 Jul 2025, 329 days before the data date Past contract end Third Kufa bridge (Imam Ali bridge) Najaf Roads and bridges No. 301 Contract ends 5 Sept 2026 On track Second carriageway of the overland Hajj road, phase three, 27 km Najaf Roads and bridges No. 302 Contract ended 4 Sept 2025, 270 days before the data date Past contract end Maintenance and rehabilitation of the quarries road, old lane, 27 km, Najaf Najaf Roads and bridges No. 303 Contract ended 1 Nov 2025, 212 days before the data date Past contract end Fifth Kufa bridge Najaf Roads and bridges No. 304 Contract ends 22 Jun 2028 On track Second carriageway of the Kut, Badra and Mehran road including the Kalal Badra bridge (76 km), phase two of 36.4 km with a bridge over Wadi Kalal and an overpass at the Badra city entrance, Wasit Wasit Roads and bridges No. 305 Contract ended 10 Jul 2025, 326 days before the data date Past contract end Second Numaniya bridge Wasit Roads and bridges No. 306 14.2 points below planned progress Behind plan Widening and rehabilitation of the Kut to Baghdad main road within Wasit, 60 km (phase one) Wasit Roads and bridges No. 307 Contract ended 19 Oct 2024, 590 days before the data date Past contract end Maintenance of the old Kut, Badra and Mehran road, Wasit Wasit Roads and bridges No. 308 Contract ends 4 Jun 2026 On track Second carriageway of the Suwaira to Jabla road, Expressway No. 1 Wasit Roads and bridges No. 309 Contract ends 30 Sept 2028 On track Second carriageway of the Dabbouni to Jassan road and maintenance of the old road Wasit Roads and bridges No. 310 Contract ends 7 Jan 2029 On track Rehabilitation and widening of the Kut to Baghdad main road, 71.5 km Wasit Roads and bridges No. 311 Contract ends 3 Mar 2029 On track Diwaniyah to Hilla main road, phase one, 25.3 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 312 Contract ends 10 Jun 2026 On track Maintenance of the Salam to Islah road, 15 km Maysan Roads and bridges No. 313 Contract ended 5 Sept 2025, 269 days before the data date Past contract end Dur al-Naft concrete bridge and approaches Maysan Roads and bridges No. 314 Contract ended 22 Apr 2026, 40 days before the data date Past contract end Abdullah bin Ali concrete bridge and approaches Maysan Roads and bridges No. 315 Contract ended 22 Apr 2026, 40 days before the data date Past contract end Qal'at Salih concrete bridge and approaches Maysan Roads and bridges No. 316 Contract ended 22 Apr 2026, 40 days before the data date Past contract end Rehabilitation and maintenance of the Amarah, Mashrah, Ghuzaila and Sheeb border road, 64.5 km Maysan Roads and bridges No. 317 Contract ended 15 Mar 2026, 78 days before the data date Past contract end Rehabilitation and maintenance of the Amarah, Butaira and Fajr road, outbound lane, 80 km Maysan Roads and bridges No. 318 Contract ended 4 May 2026, 28 days before the data date Past contract end Al Khalil (Al Ammar) bridge, Shatra district Dhi Qar Roads and bridges No. 319 Contract ended 29 Jun 2025, 337 days before the data date Past contract end Remaining works on the north Nasiriyah bridge and approaches (phase one, river bridge), Dhi Qar (at the expense of the defaulting contractor) Dhi Qar Roads and bridges No. 320 Contract ended 3 May 2026, 29 days before the data date Past contract end Rehabilitation and development of the single Dutch bridge Dhi Qar Roads and bridges No. 321 Contract ended 10 May 2026, 22 days before the data date Past contract end Link from Nasiriyah to Expressway No. 1, 24.6 km Dhi Qar Roads and bridges No. 322 66.6 points below planned progress Behind plan Al-Rehab to Ain Saida and Al-Busaya road, 50 km, Muthanna Muthanna Roads and bridges No. 323 Contract ended 24 Jul 2023, 1,043 days before the data date Past contract end Second carriageway of the Samawah to Mamlaha road (Abdullah Abu Najm road), 19.6 km with three bridges, Muthanna Muthanna Roads and bridges No. 324 Contract ended 23 Jun 2023, 1,074 days before the data date Past contract end Maintenance of the Samawah to Nasiriyah road, old lane, 14 km Muthanna Roads and bridges No. 325 Contract ended 6 Sept 2025, 268 days before the data date Past contract end Rehabilitation of the Jumaima border crossing Muthanna Roads and bridges No. 326 Contract ended 21 Aug 2025, 284 days before the data date Past contract end Removal of the temporary steel bridge and construction of the Al-Ali concrete bridge Basra Roads and bridges No. 327 Contract ended 22 Mar 2026, 71 days before the data date Past contract end Martyr Izz al-Din Salim bridge, 312 m, Basra Basra Roads and bridges No. 328 30.5 points below planned progress Behind plan Second carriageway of the Butaira, Fajr and Al Budair road, 52.35 km Several provinces Roads and bridges No. 329 Contract ended 1 Nov 2025, 212 days before the data date Past contract end Settlement of accounts for completed and cancelled projects Several provinces Roads and bridges No. 330 No progress data Rehabilitation of the Baghdad to Abu Ghraib expressway Several provinces Roads and bridges No. 331 Contract ended 7 Dec 2025, 176 days before the data date Past contract end Expressway section T/6, right lane, km 0 to km 47 Several provinces Roads and bridges No. 332 Contract ended 20 May 2025, 377 days before the data date Past contract end Bridges of expressway section T/6, km 0 to km 144.8 Several provinces Roads and bridges No. 333 Contract ended 31 Aug 2023, 1,005 days before the data date Past contract end Link from the government complex to Expressway No. 1 at km 100 Several provinces Roads and bridges No. 334 Contract ended 17 Dec 2025, 166 days before the data date Past contract end Link from Fallujah University to Expressway No. 1 Several provinces Roads and bridges No. 335 Contract ended 19 Mar 2026, 74 days before the data date Past contract end Opening the route of the fourth ring road Several provinces Roads and bridges No. 336 77.4 points below planned progress Behind plan Expressway No. 1 rehabilitation, section T/4, phase one, 105 km Several provinces Roads and bridges No. 337 Contract ended 27 Mar 2023, 1,162 days before the data date Past contract end Link from Karbala to the expressway Several provinces Roads and bridges No. 338 11 points below planned progress Behind plan Link from the Hamza road to Expressway No. 1 Several provinces Roads and bridges No. 339 23 points below planned progress Behind plan Second carriageway at Tarmiya, Baghdad to Mosul entrance, 13 km, Baghdad Several provinces Roads and bridges No. 340 Contract ended 12 Jun 2024, 719 days before the data date Past contract end Rehabilitation and maintenance of Expressway No. 1, section T/4, phase two Several provinces Roads and bridges No. 341 Contract ends 22 Feb 2029 On track Completion works for the middle and final parts of the second carriageway of the Kisik to Rabia road, Nineveh Nineveh Roads and bridges No. 342 Completed Development of the Badriya to Baadhra road, Nineveh Nineveh Roads and bridges No. 343 Completed Completion works for the sixth Mosul bridge and approaches Nineveh Roads and bridges No. 344 Completed Rehabilitation of the Baqaq bridge (second carriageway) Nineveh Roads and bridges No. 345 Completed Rehabilitation and replacement of the second Quri Chay bridge on the old lane and approaches Kirkuk Roads and bridges No. 346 Completed Construction and rehabilitation of roads in Saadiya, Mansuriya and Jizani al-Imam linked to the Baghdad to Kirkuk road, 33.61 km Diyala Roads and bridges No. 347 Completed Second carriageway of the Jalawla to Qara Tapa road, 36.1 km Diyala Roads and bridges No. 348 Completed Rehabilitation and maintenance of the Baghdad to Kirkuk road, 64 km Diyala Roads and bridges No. 349 Completed Second carriageway of the Ramadi to Haditha road, 33 km, phase three, including Wadi Hajlan Anbar Roads and bridges No. 350 Completed Haditha bridge and approaches, 548 m, Anbar Anbar Roads and bridges No. 351 Completed Maintenance of the Ramadi to Hit road, 17 km Anbar Roads and bridges No. 352 Completed Rehabilitation of the Wadi Ghadaf bridge on the 160 km Nukhaib road, at km 54 Anbar Roads and bridges No. 353 Completed Fourth Fallujah bridge Anbar Roads and bridges No. 354 Completed Rehabilitation and maintenance of the Ramadi to Qaim main road from the Muhammadi roundabout to the Bastamiya checkpoint, 32 km westwards Anbar Roads and bridges No. 355 Completed Completion works for the Haditha bridge approaches Anbar Roads and bridges No. 356 Completed Maintenance, resurfacing and shoulder stabilisation of the Ramadi to Qaim main road from km 30.1 to km 47.1 (counting from the Haditha junction) Anbar Roads and bridges No. 357 Completed Rehabilitation of the road over the drain (Albu Haddad and Albu Shubail) Anbar Roads and bridges No. 358 Completed Rehabilitation of the road linking the villages of Albu Dhalil, Albu Dhib and Albu Dimna, 1,000 m long and 20 m wide Anbar Roads and bridges No. 359 Completed Maintenance of the Adhamiya bridge Baghdad Roads and bridges No. 360 Completed Maintenance and rehabilitation of the Muthanna bridge Baghdad Roads and bridges No. 361 Completed Bab al-Muadham bridge Baghdad Roads and bridges No. 362 Completed Shuhada bridge Baghdad Roads and bridges No. 363 Completed Aimma bridge Baghdad Roads and bridges No. 364 Completed Maintenance of the steel (Awadil) bridge over the Diyala river Baghdad Roads and bridges No. 365 Completed Design and construction of the new Baghdad Court intersection (formerly the General Security intersection) Baghdad Roads and bridges No. 366 Completed Kardhiya bridge in Kut, phase two Wasit Roads and bridges No. 367 Completed Remaining works on the Kardhiya bridge in Kut, phase one Wasit Roads and bridges No. 368 Completed Second carriageway of the Ghammas junction to Hamza al-Sharqi road, 19 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 369 Completed Maintenance and rehabilitation of the Diwaniyah to Najaf road, return lane, 19 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 370 Completed Maintenance of the Sunniya to Albu Nail road, 10 km, Sunniya district Al-Qadisiyah (Diwaniyah) Roads and bridges No. 371 Completed Replacement of the Mohammed Sadiq al-Sadr bridge Al-Qadisiyah (Diwaniyah) Roads and bridges No. 372 Completed Rehabilitation and maintenance of the State Farm road, 12.91 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 373 Completed Rehabilitation of the Diwaniyah, Al Budair and Fajr road (return side), 38 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 374 Completed Maintenance of the Madhiya road in Ghammas district, 10.5 km Al-Qadisiyah (Diwaniyah) Roads and bridges No. 375 Completed Rehabilitation of the road linking Sumer to Imam Ibn al-Abbas Al-Qadisiyah (Diwaniyah) Roads and bridges No. 376 Completed Sababat concrete bridge Maysan Roads and bridges No. 377 Completed Maimuna bridge Maysan Roads and bridges No. 378 Completed Second carriageway of the Butaira to Amarah road, 5.148 km Maysan Roads and bridges No. 379 Completed Rehabilitation and maintenance of the Kut to Nasiriyah road, 28 km Dhi Qar Roads and bridges No. 380 Completed Rehabilitation and maintenance of 8.3 km of scattered sections of the Fajr to Al Budair road Dhi Qar Roads and bridges No. 381 Completed Maintenance of the Samawah, Mamlaha and Mamlaha intersection road, 23 km, and rehabilitation of three single lane bridges on the main road Muthanna Roads and bridges No. 382 Completed Khidr concrete bridge (phase two) Muthanna Roads and bridges No. 383 Completed Maintenance and furnishing of the Nasiriyah to Samawah road, 24 km, both directions Muthanna Roads and bridges No. 384 Completed Maintenance of the Hilla to Kish road, 14 km (return lane) Several provinces Roads and bridges No. 385 Completed Fixed pedestrian bridge in the Kraiyat area, Baghdad Several provinces Roads and bridges No. 386 Completed Samawah branch road works (left lane), km 1.4 to km 27.144, Muthanna Several provinces Roads and bridges No. 387 Completed Maintenance of the Bathaa bridge at km 142.7 Several provinces Roads and bridges No. 388 Completed Rehabilitation of the heavy vehicle and tanker lane at the Suqur checkpoint Several provinces Roads and bridges No. 389 Completed

Source: Ministry of Construction, status as of 1 Jun 2026Details

How status is worked out

Status is calculated from the official numbers only. Past contract end means the contract end date was before 1 Jun 2026 and progress is below 100%. Behind plan means actual progress is more than 10 points below planned. What is being built is our own grouping, read from the official project names. A project can be in more than one group, and offices and other buildings are in none. More about the data