Past contract end
Rehabilitation of Jalawla General Hospital
Buildings project No. 2 in Diyala.
تأهيل مستشفى جلولاء العام
Actual progress 62% as of 1 Jun 2026
Where the plan says it should be 100% 38 points behind
Progress against plan
Contract ended 18 Apr 2026, 44 days before the data date
Timeline
2024
2026
- Started
- 12 Sept 2024
- Contract end
- 18 Apr 2026
- Running for
- 1.7 years
- Data as of
- 1 Jun 2026