How project status is derived
For each project the ministry publishes planned progress, actual progress and the contract end date, as of 1 Jun 2026. We classify each project from those figures only:
- Completed: actual progress is 100% or more.
- Past contract end: the contract end date is before 1 Jun 2026 and the project is not complete.
- Behind plan: actual progress is more than 10 points below planned.
- On track: none of the above.
- No progress data: no actual progress figure was published.
We do not comment on or rate projects, and we do not rank provinces or companies. Contractor names are only published after a manual review.
Language
The site is in English for now; Arabic and Kurdish versions are planned. The ministry publishes project names in Arabic only. The English project names are our own translations and have not been reviewed yet, so the official Arabic name is always shown on the project page. Border crossing names are shortened from the commission's English names.
Government service names are published in Arabic only. The English service and agency names are also our own translations, not yet reviewed, and each service page shows the official Arabic name. Whether a service can be paid online is read from its official name.
Known gaps
- Most datasets do not cover the Kurdistan Region.
- 43 projects have no contract end date, and 30 have no actual progress figure.
- The students file lists Muthanna twice and has no row for Al-Qadisiyah, so we show no student figures for either.