Past contract end
Supply, construction, operation and maintenance of completion works for stormwater and sewage networks with lift stations and treatment plant for Baquba, phase 2, Diyala
Sewage project No. 130 in Diyala.
تجهيز وتنفيذ وتشغيل وصيانة الاعمال التكميلية لشبكات مياه الامطار والثقيلة مع محطات الرفع ومحطة المعالجة لمدينة بعقوبة م 2 / محافظة ديالى
Actual progress 73% as of 1 Jun 2026
Where the plan says it should be 80% 7 points behind
Progress against plan
Contract ended 27 Feb 2026, 94 days before the data date
Timeline
2023
2026
- Started
- 5 Jun 2023
- Contract end
- 27 Feb 2026
- Running for
- 3 years
- Data as of
- 1 Jun 2026