Behind plan
Link from Nasiriyah to Expressway No. 1, 24.6 km
Roads and bridges project No. 322 in Dhi Qar.
مشروع ربط الناصرية بالمرور السريع رقم(1) بطول 24.6 كم
Actual progress 30.1% as of 1 Jun 2026
Where the plan says it should be 96.7% 66.6 points behind
Progress against plan
66.6 points below planned progress
Timeline
2023
2026
- Started
- 25 May 2023
- Contract end
- 4 Jul 2026
- Running for
- 3 years
- Data as of
- 1 Jun 2026