Completed
Rehabilitation and maintenance of 8.3 km of scattered sections of the Fajr to Al Budair road
Roads and bridges project No. 381 in Dhi Qar.
مشروع تاهيل وصيانة 8.3كم متفرقة من طريق فجر - ال بدير
Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%
Progress against plan
Timeline
2025
Contract end
2026
- Started
- 26 Feb 2025
- Contract end
- 1 Oct 2025
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026