Past contract end

Zurbatiyah border crossing, commercial section

Buildings project No. 21 in Wasit.

منفذ زرباطية الحدودي / الجانب التجاري

Actual progress 7% as of 1 Jun 2026
Where the plan says it should be 40.2% 33.2 points behind

Progress against plan

Contract ended 17 May 2026, 15 days before the data date

Timeline

Started
14 Jun 2024
Contract end
17 May 2026
Running for
2 years
Data as of
1 Jun 2026