On track

Maimuna water project, capacity 2,000 m3 per hour

Water project No. 243 in Maysan.

مشروع ماء الميمونة بطاقة 2000م3/ساعة

Actual progress 16.4% as of 1 Jun 2026
Where the plan says it should be 13.6%

Progress against plan

Contract ends 10 Mar 2028

Timeline

Started
22 Sept 2025
Contract end
10 Mar 2028
Running for
0.7 years
Data as of
1 Jun 2026