On track

Residential complex in Anbar, Jubail and Kharab

Housing project No. 77 in Anbar.

انشاء مجمع سكني في محافظة الانبار/ جبيل والخراب

Actual progress 85.4% as of 1 Jun 2026
Where the plan says it should be 72.3%

Progress against plan

Contract ends 16 Sept 2027

Timeline

Started
15 May 2023
Contract end
16 Sept 2027
Running for
3 years
Data as of
1 Jun 2026