On track

Second carriageway of the Mosul to Kirkuk road, 124.43 km, in Kirkuk and Nineveh

Roads and bridges project No. 256 in Nineveh.

مشروع انشاء الممر الثاني لطريق موصل - كركوك بطول 124,43 كم ضمن محافظتي كركوك ونينوى

Actual progress 83.5% as of 1 Jun 2026
Where the plan says it should be 78.5%

Progress against plan

Contract ends 24 Apr 2027

Timeline

Started
6 Aug 2023
Contract end
24 Apr 2027
Running for
2.8 years
Data as of
1 Jun 2026