On track

New Kuwair bridge, second carriageway next to the old Kuwair bridge

Roads and bridges project No. 259 in Nineveh.

انشاء جسر الكوير الجديد الممر الثاني المحاذي لجسر الكوير القديم

When will the New Kuwair bridge, second carriageway next to the old Kuwair bridge be finished? The contract end date is 21 Jun 2028. As of 1 Jun 2026 the Ministry of Construction reported it 0.2% complete, against 0% planned. The published data gives no revised completion date.

Actual progress 0.2% as of 1 Jun 2026
Where the plan says it should be 0%

Progress against plan

Contract ends 21 Jun 2028

Timeline

Started
4 Jan 2026
Contract end
21 Jun 2028
Running for
0.4 years
Data as of
1 Jun 2026