On track
New Kuwair bridge, second carriageway next to the old Kuwair bridge
Roads and bridges project No. 259 in Nineveh.
انشاء جسر الكوير الجديد الممر الثاني المحاذي لجسر الكوير القديم
When will the New Kuwair bridge, second carriageway next to the old Kuwair bridge be finished? The contract end date is 21 Jun 2028. As of 1 Jun 2026 the Ministry of Construction reported it 0.2% complete, against 0% planned. The published data gives no revised completion date.
Actual progress 0.2% as of 1 Jun 2026
Where the plan says it should be 0%
Progress against plan
Contract ends 21 Jun 2028
Timeline
2026
2028
- Started
- 4 Jan 2026
- Contract end
- 21 Jun 2028
- Running for
- 0.4 years
- Data as of
- 1 Jun 2026