Completed

Completion works for the middle and final parts of the second carriageway of the Kisik to Rabia road, Nineveh

Roads and bridges project No. 342 in Nineveh.

مشروع الاعمال التكميلية للممر الثاني لطريق كسك ربيعة بجزئيه الوسطي والأخير في محافظة نينوى

Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%

Progress against plan

Timeline

Started
12 Jan 2023
Contract end
16 Jul 2025
Running for
3.4 years
Data as of
1 Jun 2026