Past contract end

Rehabilitation of the Sinjar to Umm Jurais road, 35 km long and 7.4 m wide

Roads and bridges project No. 258 in Nineveh.

تأهيل طريق سنجار ام جريص بطول 35 كم وعرض 7.40م

Actual progress 62.3% as of 1 Jun 2026
Where the plan says it should be 100% 37.7 points behind

Progress against plan

Contract ended 22 Jan 2026, 130 days before the data date

Timeline

Started
10 Aug 2025
Contract end
22 Jan 2026
Running for
0.8 years
Data as of
1 Jun 2026