Completed

Second carriageway of the Butaira to Amarah road, 5.148 km

Roads and bridges project No. 379 in Maysan.

انشاء الممر الثاني لطريق بتيرة -عمارة بطول 5.148 كم

Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%

Progress against plan

Timeline

Started
14 Jan 2024
Contract end
10 Apr 2025
Running for
2.4 years
Data as of
1 Jun 2026