Past contract end
Rehabilitation and maintenance of the Amarah, Mashrah, Ghuzaila and Sheeb border road, 64.5 km
Roads and bridges project No. 317 in Maysan.
تأهيل وصيانة طريق عمارة - مشرح -غزيلة - شيب الحدودي بطول 64.5 كم
Actual progress 61% as of 1 Jun 2026
Where the plan says it should be 100% 39 points behind
Progress against plan
Contract ended 15 Mar 2026, 78 days before the data date
Timeline
2025
Contract end
2026
- Started
- 24 Mar 2025
- Contract end
- 15 Mar 2026
- Running for
- 1.2 years
- Data as of
- 1 Jun 2026