Past contract end

Completion works for street paving and development of the Zahraa and Batool residential neighbourhoods, Ali al-Gharbi district

Municipal services project No. 201 in Maysan.

الاعمال التكميلية لمشروع تبليط الشوارع وتطوير الاحياء والسكنية (الزهراء والبتول) قضاء علي الغربي

Actual progress 92.6% as of 1 Jun 2026
Where the plan says it should be 100% 7.4 points behind

Progress against plan

Contract ended 15 May 2025, 382 days before the data date

Timeline

Started
18 Nov 2023
Contract end
15 May 2025
Running for
2.5 years
Data as of
1 Jun 2026