On track

Widening of the Haidariya to Najaf and Karbala road, 15.64 km

Roads and bridges project No. 299 in Najaf.

توسعة وتطويق طريق الحيدرية - النجف كربلاء بطول 15.64 كم

Actual progress 82.6% as of 1 Jun 2026
Where the plan says it should be 89.5% 6.9 points behind

Progress against plan

Contract ends 13 Jul 2026

Timeline

Started
6 Sept 2024
Contract end
13 Jul 2026
Running for
1.7 years
Data as of
1 Jun 2026