Past contract end
Maintenance and rehabilitation of the quarries road, old lane, 27 km, Najaf
Roads and bridges project No. 303 in Najaf.
اعمال صيانة وتاهيل طريق المقالع الممر القديم بطول 27كم / النجف
Actual progress 74.5% as of 1 Jun 2026
Where the plan says it should be 100% 25.5 points behind
Progress against plan
Contract ended 1 Nov 2025, 212 days before the data date
Timeline
2022
2026
- Started
- 28 Jun 2022
- Contract end
- 1 Nov 2025
- Running for
- 3.9 years
- Data as of
- 1 Jun 2026