Road projects in Najaf
The Ministry of Construction lists 6 road projects in Najaf: 3 past contract end, 1 behind plan, 2 on track, as of 1 Jun 2026.
On track2
Behind plan1
Past contract end3
Overland Hajj road (239 km), phase one, 50 km from km 27 to km 77, Najaf Contract ended 7 Jul 2025, 329 days before the data date Past contract end Second carriageway of the overland Hajj road, phase three, 27 km Contract ended 4 Sept 2025, 270 days before the data date Past contract end Maintenance and rehabilitation of the quarries road, old lane, 27 km, Najaf Contract ended 1 Nov 2025, 212 days before the data date Past contract end Overland Hajj road (239 km), phase two, 50 km from km 77 to km 127, Najaf 11.5 points below planned progress Behind plan Second carriageway linking the Kifl to Qasim expressway, 30 km, Najaf (infrastructure) Contract ends 29 Aug 2028 On track Widening of the Haidariya to Najaf and Karbala road, 15.64 km Contract ends 13 Jul 2026 On track
Source: Ministry of Construction, status as of 1 Jun 2026Details