On track

Second carriageway linking the Kifl to Qasim expressway, 30 km, Najaf (infrastructure)

Roads and bridges project No. 297 in Najaf.

مشروع ربط طريق المرور السريع كفل قاسم الممر الثاني بطول 30 كم في محافظة النجف ( بنى تحتية)

Actual progress 15.6% as of 1 Jun 2026
Where the plan says it should be 18.3% 2.7 points behind

Progress against plan

Contract ends 29 Aug 2028

Timeline

Started
25 Aug 2025
Contract end
29 Aug 2028
Running for
0.8 years
Data as of
1 Jun 2026