Behind plan

Overland Hajj road (239 km), phase two, 50 km from km 77 to km 127, Najaf

Roads and bridges project No. 298 in Najaf.

انشاء طريق الحج البري بطول ( 239) كم المرحلة الثانية بطول (50) كم للمقطع (000+77) لغاية ـ(000+127) / النجف

Actual progress 79.5% as of 1 Jun 2026
Where the plan says it should be 91% 11.5 points behind

Progress against plan

11.5 points below planned progress

Timeline

Started
30 Dec 2013
Contract end
21 Aug 2026
Running for
12.4 years
Data as of
1 Jun 2026