On track
Second carriageway of the Suwaira to Jabla road, Expressway No. 1
Roads and bridges project No. 309 in Wasit.
الممر الثاني لطريق ( صويرة - جبله) المرور السريع السريع رقم 1
Actual progress 2% as of 1 Jun 2026
Where the plan says it should be 3% 1 points behind
Progress against plan
Contract ends 30 Sept 2028
Timeline
2026
2028
- Started
- 4 Jan 2026
- Contract end
- 30 Sept 2028
- Running for
- 0.4 years
- Data as of
- 1 Jun 2026