On track
Second carriageway of the Dabbouni to Jassan road and maintenance of the old road
Roads and bridges project No. 310 in Wasit.
الممر الثاني لطريق (دبوني-جصان) وصيانة الطريق القديم
Actual progress 0.6% as of 1 Jun 2026
Where the plan says it should be 5.1% 4.5 points behind
Progress against plan
Contract ends 7 Jan 2029
Timeline
2026
2029
- Started
- 4 Jan 2026
- Contract end
- 7 Jan 2029
- Running for
- 0.4 years
- Data as of
- 1 Jun 2026