Second carriageway of the Kut, Badra and Mehran road including the Kalal Badra bridge (76 km), phase two of 36.4 km with a bridge over Wadi Kalal and an overpass at the Badra city entrance, Wasit
Roads and bridges project No. 305 in Wasit.
انشاء الممر الثاني (كوت / بدرة /مهران) بضمنها جسر (كلال /بدرة) بطول 76 كم المرحلة الثانية بطول 36.4 كم مع جسر على وادي كلال وتقاطع مجسر عند مدخل مدينة بدرة في محافظة واسط
When will the Second carriageway of the Kut, Badra and Mehran road including the Kalal Badra bridge (76 km), phase two of 36.4 km with a bridge over Wadi Kalal and an overpass at the Badra city entrance, Wasit be finished? The contract end date was 10 Jul 2025. As of 1 Jun 2026 the Ministry of Construction reported it 91.5% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 91.5% as of 1 Jun 2026
Where the plan says it should be 100% 8.5 points behind
Progress against plan
Contract ended 10 Jul 2025, 326 days before the data date
Timeline
2014
2026
- Started
- 22 Dec 2014
- Contract end
- 10 Jul 2025
- Running for
- 11.4 years
- Data as of
- 1 Jun 2026