Behind plan

Second Numaniya bridge

Roads and bridges project No. 306 in Wasit.

انشاء جسر النعمانية الثاني

When will the Second Numaniya bridge be finished? The contract end date is 29 Oct 2026. As of 1 Jun 2026 the Ministry of Construction reported it 40.5% complete, against 54.7% planned. The published data gives no revised completion date.

Actual progress 40.5% as of 1 Jun 2026
Where the plan says it should be 54.7% 14.2 points behind

Progress against plan

14.2 points below planned progress

Timeline

Started
8 Mar 2025
Contract end
29 Oct 2026
Running for
1.2 years
Data as of
1 Jun 2026