Behind plan
Second Numaniya bridge
Roads and bridges project No. 306 in Wasit.
انشاء جسر النعمانية الثاني
When will the Second Numaniya bridge be finished? The contract end date is 29 Oct 2026. As of 1 Jun 2026 the Ministry of Construction reported it 40.5% complete, against 54.7% planned. The published data gives no revised completion date.
Actual progress 40.5% as of 1 Jun 2026
Where the plan says it should be 54.7% 14.2 points behind
Progress against plan
14.2 points below planned progress
Timeline
2025
2026
- Started
- 8 Mar 2025
- Contract end
- 29 Oct 2026
- Running for
- 1.2 years
- Data as of
- 1 Jun 2026