Bridge projects in Wasit
The Ministry of Construction lists 4 bridge projects in Wasit: 1 past contract end, 1 behind plan, 2 completed, as of 1 Jun 2026.
Completed2
Behind plan1
Past contract end1
Second carriageway of the Kut, Badra and Mehran road including the Kalal Badra bridge (76 km), phase two of 36.4 km with a bridge over Wadi Kalal and an overpass at the Badra city entrance, Wasit Contract ended 10 Jul 2025, 326 days before the data date Past contract end Second Numaniya bridge 14.2 points below planned progress Behind plan Kardhiya bridge in Kut, phase two Completed Remaining works on the Kardhiya bridge in Kut, phase one Completed
Source: Ministry of Construction, status as of 1 Jun 2026Details