Past contract end

Widening and rehabilitation of the Kut to Baghdad main road within Wasit, 60 km (phase one)

Roads and bridges project No. 307 in Wasit.

تعريض وتأهيل الطريق العام كوت / بغداد ضمن محافظة واسط بطول 60 كم (المرحلة الأولى)

Actual progress 97% as of 1 Jun 2026
Where the plan says it should be 100% 3 points behind

Progress against plan

Contract ended 19 Oct 2024, 590 days before the data date

Timeline

Started
15 Dec 2014
Contract end
19 Oct 2024
Running for
11.5 years
Data as of
1 Jun 2026