Past contract end
Overpass intersection in Muthanna, Quds intersection
Municipal services project No. 204 in Muthanna.
انشاء تقاطع مجسر في محافظة المثنى /تقاطع القدس
When will the Overpass intersection in Muthanna, Quds intersection be finished? The contract end date was 13 Oct 2024. As of 1 Jun 2026 the Ministry of Construction reported it 99.8% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 99.8% as of 1 Jun 2026
Where the plan says it should be 100% 0.2 points behind
Progress against plan
Contract ended 13 Oct 2024, 596 days before the data date
Timeline
2014
2026
- Started
- 1 Nov 2014
- Contract end
- 13 Oct 2024
- Running for
- 11.6 years
- Data as of
- 1 Jun 2026