Past contract end

Expressway No. 1 rehabilitation, section T/4, phase one, 105 km

Roads and bridges project No. 337 across several provinces.

تأهيل طريق المرور سريع رقم (1) جزء ط/4/المرحلة الأولى بطول 105كم / المرور السريع

Actual progress 77.4% as of 1 Jun 2026
Where the plan says it should be 100% 22.6 points behind

Progress against plan

Contract ended 27 Mar 2023, 1,162 days before the data date

Timeline

Started
22 Dec 2013
Contract end
27 Mar 2023
Running for
12.4 years
Data as of
1 Jun 2026