Past contract end
Expressway No. 1 rehabilitation, section T/4, phase one, 105 km
Roads and bridges project No. 337 across several provinces.
تأهيل طريق المرور سريع رقم (1) جزء ط/4/المرحلة الأولى بطول 105كم / المرور السريع
Actual progress 77.4% as of 1 Jun 2026
Where the plan says it should be 100% 22.6 points behind
Progress against plan
Contract ended 27 Mar 2023, 1,162 days before the data date
Timeline
2013
Contract end
2026
- Started
- 22 Dec 2013
- Contract end
- 27 Mar 2023
- Running for
- 12.4 years
- Data as of
- 1 Jun 2026