Past contract end

Sindiya bridge, 336 m

Roads and bridges project No. 270 in Diyala.

جسر السندية بطول 336م

When will the Sindiya bridge, 336 m be finished? The contract end date was 2 Aug 2024. As of 1 Jun 2026 the Ministry of Construction reported it 39.5% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 39.5% as of 1 Jun 2026
Where the plan says it should be 100% 60.5 points behind

Progress against plan

Contract ended 2 Aug 2024, 668 days before the data date

Timeline

Started
1 May 2012
Contract end
2 Aug 2024
Running for
14.1 years
Data as of
1 Jun 2026