Past contract end

Hamrin lake concrete bridge and rehabilitation of the Muqdadiya to Saadiya main road (Hamrin lake basin)

Roads and bridges project No. 267 in Diyala.

انشاء جسر بحيرة حمرين الكونكريتي وتاهيل الطريق العام المقدادية - السعدية (ضمن حوض بحيرة حمرين)

When will the Hamrin lake concrete bridge and rehabilitation of the Muqdadiya to Saadiya main road (Hamrin lake basin) be finished? The contract end date was 19 May 2026. As of 1 Jun 2026 the Ministry of Construction reported it 88.4% complete, against 99% planned. The published data gives no revised completion date.

Actual progress 88.4% as of 1 Jun 2026
Where the plan says it should be 99% 10.6 points behind

Progress against plan

Contract ended 19 May 2026, 13 days before the data date

Timeline

Started
28 Jun 2022
Contract end
19 May 2026
Running for
3.9 years
Data as of
1 Jun 2026