Past contract end

Various roads across Khalis and its subdistricts in Diyala

Roads and bridges project No. 271 in Diyala.

طرق متفرقة في عموم الخالص ونواحيها في محافظة ديالى

Actual progress 89% as of 1 Jun 2026
Where the plan says it should be 100% 11 points behind

Progress against plan

Contract ended 13 Sept 2025, 261 days before the data date

Timeline

Started
7 Jan 2025
Contract end
13 Sept 2025
Running for
1.4 years
Data as of
1 Jun 2026