Rehabilitation and maintenance of the Baghdad to Kirkuk road, 110 km
Roads and bridges project No. 268 in Diyala.
مشروع تأهيل وصيانة طريق بغداد - كركوك بطول 110كم
Actual progress 86% as of 1 Jun 2026
Where the plan says it should be 100% 14 points behind
Progress against plan
Contract ended 20 Jul 2024, 681 days before the data date
Timeline
2022
Contract end
2026
- Started
- 13 Jan 2022
- Contract end
- 20 Jul 2024
- Running for
- 4.4 years
- Data as of
- 1 Jun 2026