Past contract end

Rehabilitation and maintenance of the Baghdad to Kirkuk road, 110 km

Roads and bridges project No. 268 in Diyala.

مشروع تأهيل وصيانة طريق بغداد - كركوك بطول 110كم

Actual progress 86% as of 1 Jun 2026
Where the plan says it should be 100% 14 points behind

Progress against plan

Contract ended 20 Jul 2024, 681 days before the data date

Timeline

Started
13 Jan 2022
Contract end
20 Jul 2024
Running for
4.4 years
Data as of
1 Jun 2026