Past contract end
Rehabilitation of the main road from Jalawla bridge to the Halwan intersection, Jalawla, Diyala
Municipal services project No. 194 in Diyala.
تأهيل الشارع العام من جسر جلولاء الى تقاطع حلوان /جلولاء في محافظة ديالى
When will the Rehabilitation of the main road from Jalawla bridge to the Halwan intersection, Jalawla, Diyala be finished? The contract end date was 27 Feb 2026. As of 1 Jun 2026 the Ministry of Construction reported it 54% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 54% as of 1 Jun 2026
Where the plan says it should be 100% 46 points behind
Progress against plan
Contract ended 27 Feb 2026, 94 days before the data date
Timeline
2025
Contract end
2026
- Started
- 26 Feb 2025
- Contract end
- 27 Feb 2026
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026