Past contract end
Maintenance and stabilisation of the Mundhiriya, Imam Wais and Failaq road, 90 km, two lanes
Roads and bridges project No. 269 in Diyala.
صيانة وتثبيت طريق المنذرية-امام ويس-الفيلق بطول90كم ذو ممرين
Actual progress 42% as of 1 Jun 2026
Where the plan says it should be 100% 58 points behind
Progress against plan
Contract ended 26 Apr 2026, 36 days before the data date
Timeline
2024
2026
- Started
- 26 Aug 2024
- Contract end
- 26 Apr 2026
- Running for
- 1.8 years
- Data as of
- 1 Jun 2026