On track

Completion works for a group of roads in Saadiya, Jizani al-Imam and Mansuriya

Roads and bridges project No. 272 in Diyala.

مشروع الاعمال التكميلية لمشروع انشاء مجموعة طرق في السعدية_ جيزاني_ الامام_ المنصورية

Actual progress 59% as of 1 Jun 2026
Where the plan says it should be 64% 5 points behind

Progress against plan

Contract ends 26 Jul 2026

Timeline

Started
28 Dec 2025
Contract end
26 Jul 2026
Running for
0.4 years
Data as of
1 Jun 2026