Behind plan
Design and construction of the Kraiyat bridge, Baghdad
Roads and bridges project No. 286 in Baghdad.
مشروع تصميم وتنفيذ وانشاء جسر الكريعات في محافظة بغداد
When will the Design and construction of the Kraiyat bridge, Baghdad be finished? The contract end date is 13 Apr 2027. As of 1 Jun 2026 the Ministry of Construction reported it 8.2% complete, against 43% planned. The published data gives no revised completion date.
Actual progress 8.2% as of 1 Jun 2026
Where the plan says it should be 43% 34.8 points behind
Progress against plan
34.8 points below planned progress
Timeline
2025
2027
- Started
- 13 May 2025
- Contract end
- 13 Apr 2027
- Running for
- 1.1 years
- Data as of
- 1 Jun 2026