Past contract end

Fadhiliya concrete bridge, Baghdad

Roads and bridges project No. 280 in Baghdad.

جسر الفاضلية الكونكريتي في محافظة بغداد

When will the Fadhiliya concrete bridge, Baghdad be finished? The contract end date was 9 Feb 2026. As of 1 Jun 2026 the Ministry of Construction reported it 29.6% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 29.6% as of 1 Jun 2026
Where the plan says it should be 100% 70.4 points behind

Progress against plan

Contract ended 9 Feb 2026, 112 days before the data date

Timeline

Started
23 Feb 2025
Contract end
9 Feb 2026
Running for
1.3 years
Data as of
1 Jun 2026