Design and construction of an overpass at the Refinery intersection, linking the Double Decker bridge to the Suspension bridge, and a tunnel at Ahmed Orabi square, Baghdad

Roads and bridges project No. 284 in Baghdad.

تصميم وتنفيذ وانشاء مجسر في تقاطع المصافي و ربط جسر الطابقين بجسر المعلق و انشاء نفق في تقاطع ساحة احمد عرابي في محافظة بغداد

When will the Design and construction of an overpass at the Refinery intersection, linking the Double Decker bridge to the Suspension bridge, and a tunnel at Ahmed Orabi square, Baghdad be finished? The contract end date was 20 Sept 2025. As of 1 Jun 2026 the Ministry of Construction reported it 88.5% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 88.5% as of 1 Jun 2026
Where the plan says it should be 100% 11.5 points behind

Progress against plan

Contract ended 20 Sept 2025, 254 days before the data date

Timeline

Started
29 Jan 2024
Contract end
20 Sept 2025
Running for
2.3 years
Data as of
1 Jun 2026