Behind plan

Design and construction of the Zafaraniya bridge on the Dora to Yusufiya expressway road, reaching Harith bin Kalda street, with an overpass on the Dora to Yusufiya road, Baghdad

Roads and bridges project No. 281 in Baghdad.

تصميم وتنفيذ و انشاء جسر الزعفرانية بطريق دورة – يوسفية للمرور السريع وصولا الى شارع حارث بن كلدة ومجسر على طريق دورة يوسفية في محافظة بغداد

When will the Design and construction of the Zafaraniya bridge on the Dora to Yusufiya expressway road, reaching Harith bin Kalda street, with an overpass on the Dora to Yusufiya road, Baghdad be finished? The contract end date is 31 Dec 2026. As of 1 Jun 2026 the Ministry of Construction reported it 81% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 81% as of 1 Jun 2026
Where the plan says it should be 100% 19 points behind

Progress against plan

19 points below planned progress

Timeline

Started
9 Sept 2023
Contract end
31 Dec 2026
Running for
2.7 years
Data as of
1 Jun 2026