Past contract end
Reconstruction of the Rustamiya bridge
Roads and bridges project No. 278 in Baghdad.
اعادة اعمار جسر الرستمية
When will the Reconstruction of the Rustamiya bridge be finished? The contract end date was 1 Dec 2025. As of 1 Jun 2026 the Ministry of Construction reported it 81% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 81% as of 1 Jun 2026
Where the plan says it should be 100% 19 points behind
Progress against plan
Contract ended 1 Dec 2025, 182 days before the data date
Timeline
2024
Contract end
2026
- Started
- 10 Jul 2024
- Contract end
- 1 Dec 2025
- Running for
- 1.9 years
- Data as of
- 1 Jun 2026