Past contract end

Reconstruction of the Rustamiya bridge

Roads and bridges project No. 278 in Baghdad.

اعادة اعمار جسر الرستمية

When will the Reconstruction of the Rustamiya bridge be finished? The contract end date was 1 Dec 2025. As of 1 Jun 2026 the Ministry of Construction reported it 81% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 81% as of 1 Jun 2026
Where the plan says it should be 100% 19 points behind

Progress against plan

Contract ended 1 Dec 2025, 182 days before the data date

Timeline

Started
10 Jul 2024
Contract end
1 Dec 2025
Running for
1.9 years
Data as of
1 Jun 2026