Past contract end

Grand Baghdad bridge

Roads and bridges project No. 279 in Baghdad.

جسر بغداد الكبير

When will the Grand Baghdad bridge be finished? The contract end date was 1 Apr 2026. As of 1 Jun 2026 the Ministry of Construction reported it 85% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 85% as of 1 Jun 2026
Where the plan says it should be 100% 15 points behind

Progress against plan

Contract ended 1 Apr 2026, 61 days before the data date

Timeline

Started
18 Dec 2024
Contract end
1 Apr 2026
Running for
1.5 years
Data as of
1 Jun 2026