Past contract end
Grand Baghdad bridge
Roads and bridges project No. 279 in Baghdad.
جسر بغداد الكبير
When will the Grand Baghdad bridge be finished? The contract end date was 1 Apr 2026. As of 1 Jun 2026 the Ministry of Construction reported it 85% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 85% as of 1 Jun 2026
Where the plan says it should be 100% 15 points behind
Progress against plan
Contract ended 1 Apr 2026, 61 days before the data date
Timeline
2024
2026
- Started
- 18 Dec 2024
- Contract end
- 1 Apr 2026
- Running for
- 1.5 years
- Data as of
- 1 Jun 2026