Behind plan
Ring and link roads for Ali al-Wardi city
Roads and bridges project No. 277 in Baghdad.
انشاء الطرق الحولية والرابطة لمدينة علي الوردي
Actual progress 14.2% as of 1 Jun 2026
Where the plan says it should be 46.7% 32.5 points behind
Progress against plan
32.5 points below planned progress
Timeline
2024
2026
- Started
- 12 Nov 2024
- Contract end
- 14 Oct 2026
- Running for
- 1.5 years
- Data as of
- 1 Jun 2026