Past contract end

Design and construction of the road linking the Mohammed al-Qasim expressway and the Kirkuk to Baghdad road through Basatin and Suraidat, Baghdad

Roads and bridges project No. 283 in Baghdad.

تصميم وتنفيذ الطريق الرابط بين سريع محمد القاسم و طريق كركوك- بغداد مروراً بحي البساتين و السريدات في محافظة بغداد

Actual progress 77% as of 1 Jun 2026
Where the plan says it should be 100% 23 points behind

Progress against plan

Contract ended 22 Dec 2024, 526 days before the data date

Timeline

Started
11 Sept 2023
Contract end
22 Dec 2024
Running for
2.7 years
Data as of
1 Jun 2026