Past contract end

Dora overpass on 60th street

Roads and bridges project No. 287 in Baghdad.

مشروع انشاء مجسر الدورة شارع (60)

When will the Dora overpass on 60th street be finished? The contract end date was 10 Oct 2025. As of 1 Jun 2026 the Ministry of Construction reported it 41% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 41% as of 1 Jun 2026
Where the plan says it should be 100% 59 points behind

Progress against plan

Contract ended 10 Oct 2025, 234 days before the data date

Timeline

Started
13 Jul 2025
Contract end
10 Oct 2025
Running for
0.9 years
Data as of
1 Jun 2026