Past contract end
Design and construction of the Abu Nuwas road widening and the new Jadriya overpass linked to the Nusoor square approaches via Umm al-Khanazir island, Baghdad
Roads and bridges project No. 285 in Baghdad.
تصميم وتنفيذ توسعة طريق ابو نؤاس وانشاء مجسر الجادرية الجديد وربطه بمقتربات ساحة النسور مرورابجزيرة ام الخنازير في محافظة بغداد
When will the Design and construction of the Abu Nuwas road widening and the new Jadriya overpass linked to the Nusoor square approaches via Umm al-Khanazir island, Baghdad be finished? The contract end date was 22 Feb 2025. As of 1 Jun 2026 the Ministry of Construction reported it 85.5% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 85.5% as of 1 Jun 2026
Where the plan says it should be 100% 14.5 points behind
Progress against plan
Contract ended 22 Feb 2025, 464 days before the data date
Timeline
2023
Contract end
2026
- Started
- 31 Dec 2023
- Contract end
- 22 Feb 2025
- Running for
- 2.4 years
- Data as of
- 1 Jun 2026