National water and sanitation master plan for the cities, districts and subdistricts of Karbala
Water project No. 230 in Karbala.
اعداد الخطة الوطنية الرئيسية للماء والصرف الصحي master Planلمدن واقضية ونواحي محافظة كربلاء المقدسة
Actual progress 84% as of 1 Jun 2026
Where the plan says it should be 100% 16 points behind
Progress against plan
Contract ended 12 Feb 2026, 109 days before the data date
Timeline
2025
Contract end
2026
- Started
- 12 Feb 2025
- Contract end
- 12 Feb 2026
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026