Past contract end
Maintenance of the Samawah to Nasiriyah road, old lane, 14 km
Roads and bridges project No. 325 in Muthanna.
صيانة طريق سماوة-ناصرية الممر القديم 14كم
Actual progress 90% as of 1 Jun 2026
Where the plan says it should be 100% 10 points behind
Progress against plan
Contract ended 6 Sept 2025, 268 days before the data date
Timeline
2025
Contract end
2026
- Started
- 11 Feb 2025
- Contract end
- 6 Sept 2025
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026