Past contract end

Second carriageway of the Samawah to Mamlaha road (Abdullah Abu Najm road), 19.6 km with three bridges, Muthanna

Roads and bridges project No. 324 in Muthanna.

الممر الثاني لطريق السماوة / مملحة طريق عبد الله أبو نجم 19.6 كم مع ثلاث جسور/ المثنى

When will the Second carriageway of the Samawah to Mamlaha road (Abdullah Abu Najm road), 19.6 km with three bridges, Muthanna be finished? The contract end date was 23 Jun 2023. As of 1 Jun 2026 the Ministry of Construction reported it 92% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 92% as of 1 Jun 2026
Where the plan says it should be 100% 8 points behind

Progress against plan

Contract ended 23 Jun 2023, 1,074 days before the data date

Timeline

Started
23 Oct 2012
Contract end
23 Jun 2023
Running for
13.6 years
Data as of
1 Jun 2026