Completed
Completion works for the Rifai treatment plant, design capacity 60,000 m3 per day (carried out at the expense of the defaulting company Al-Barih)
Sewage project No. 190 in Dhi Qar.
الاعمال التكميلية تجهيز وتنفيذ محطة معالجة الرفاعي بطاقة تصميمية (60000) م3/يوم (تنفيذ على حساب ناكل شركة البارح)
Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%
Progress against plan
Timeline
2013
2026
- Started
- 24 Oct 2013
- Contract end
- 10 Dec 2025
- Running for
- 12.6 years
- Data as of
- 1 Jun 2026